Rochdale
-
7 Weeks
-
£181,700
-
Refurbishment
The Works
The works included extensive re-modelling and revised construction of the café area and waiting area, which was carried out during the evening to reduce disruption to staff, patients and visitors.
New fire prevention & suppression technical designs were formed to compartmentalise all areas along with new fire doors to all entrances, fire compartmentation to all walls and carried into soffits. Other works included plastering throughout, new suspended ceilings, internal glazing decoration and flooring.
The M&E consisted of new lighting and removal and refitting heating system radiators after construction works were completed
Factors
The project's success was exhibited by its execution in a live environment, allowing the gym to remain operational throughout the refurbishment. The redesign contributed to a more sophisticated gym space, potentially sustaining membership retention. Completing the project within a short timeframe posed a significant challenge to avoid prolonged disruptions and closure of the gym. Ensuring that safety measures met JD Gyms' nationwide standards was crucial for maintaining consistency across the business.
Outcome
Greenmount Projects established a positive relationship with the JD Gyms team, laying the foundation for a potentially long-standing client relationship. Post-handover, staff members expressed positive feedback regarding the revamped gym, indicating a successful implementation. Despite the challenges, Greenmount Projects completed the project within the stipulated timeframe, meeting and exceeding client satisfaction. The positive outcomes not only resonate with the client but also contribute to the potential growth of the client relationship and Greenmount Projects' reputation in the industry.